SAFe Agile Product Management Practice Exam 2025 – The Complete All-in-One Guide to Exam Success!

Question: 1 / 400

How does SAFe utilize regular synchronization activities?

To reduce project costs

To ensure continuous alignment across teams and programs

SAFe employs regular synchronization activities primarily to ensure continuous alignment across teams and programs. This approach fosters collaboration and coordination, allowing teams to stay engaged with one another and track progress toward shared objectives. These synchronization events, such as Scrum of Scrums and ART syncs, are essential for maintaining a clear understanding of cross-team dependencies, risks, and the overall program progress.

By facilitating regular communication and touchpoints, teams can quickly address any issues that arise, adapt to changing requirements, and make informed decisions based on the collective input of different stakeholders. This alignment not only enhances team performance but also supports the delivery of value to the organization and its customers in a more cohesive manner.

The other choices do not capture the primary purpose of synchronization activities within the SAFe framework. While reducing project costs can be a secondary benefit of improved team coordination, this is not the main goal. Promoting individual achievements over team goals contradicts the collaborative ethos of SAFe, which emphasizes teamwork and collective results. Additionally, limiting communication among teams would be counterproductive and goes against the principles of transparency and collaboration that SAFe advocates.

Get further explanation with Examzify DeepDiveBeta

To promote individual achievements over team goals

To limit communication among teams

Next Question